Steel feet and insulation

31 August 2012:  [Extension] More progress!
  • The steel feet have arrived, and these have been zinc sprayed. 
  • A bit more refinement was done to the timber cut-outs for the lower part of the extension, applying some aluminium angle to the corners (see previous day's photos). 
  • The big crane-truck arrived from John Stephens bringing in my first insulation - I bought everything they had in stock, their entire 150mm PIR insulation. I will need more! 