19 Aug 2012: [Extension] 
The slab is readied for the edge wall to go in
Morning: A bit of extra skim over the slab
before the insulation is placed. edge foam is
compressible EPS
100mm slabs of extruded PS laid over slab
to insulate floor and make formwork for
edge wall
Insulation in two layers, totalling 200mm
breaking joint.
Insulation in two layers, totalling 200mm
breaking joint.
Tape the joints to prevent random
air movement between panels
Tape the joints to prevent random
air movement between panels
Forming rectangular holes because
we intended to use 50x50 square
washers with the bolts
Forming rectangular holes because
we intended to use 50x50 square
washers with the bolts
Forming rectangular holes under each
wall panel
The upright concrete wall laid
patiently, bucketfull by bucketfull.
No concrete lorries in our road!
All done now with rectangular holes...
these will take threaded rods and
steel feet for the wood panels
...then discover we cant get the square
washers, so bury the threaded road with
bolts only
Make sure the threaded rods are perfectly
vertical in all directions
Each stainless steel rod has two nuts
at the base
Harrisons, good builders, there's their
phone number
07845-162295
Slab finished. wall panels will go up
before the house wall is knocked down
and then final floor will be screeded