Wednesday, September 5, 2012

Delivery dates

4 September 2012: [Extension] We are making progress with the extension, but there are some things that we need to plan for.
  • Newform have promised to send a crew to put the PVT solar panels on if we can have the roof on by about 20 Sept as they have a large job to do locally at that time. 
  • The main windows will not be delivered until October 8th, from Spectrum/Internorm
  • Holscot have contacted us to say that we could have the new ETFE fronts for the Sunbox after October 4th. I have to organise scaffolding, both for the roof erection and for the Sunbox re-fronting. 
  • I havent booked anyone specific to put the roof metal on it. The idea is to have a metal top surface, but is this in raw thin sheet aluminium or zinc, or do we get a roofing outfit to do it with dark anodised aluminium. I'll have to look into it. 
I can see from this that I shall need the scaffolding up quite soon - probably when the main wall is up, but not the roof on. The scaffolding needs to bridge across the new extension.